Week Seven Catch-up






Oops! Missed a week. It's good to be back. Here's a quick review of what happened during week seven, although now it's midway through week eight.

Installation of studs for drywall installation is just about complete. Once the electrical work is done, the sheetrock can be installed. It's here and ready to go.

Downstairs we're setting a record for neatly and efficiently concealing the most electrical and mechanical apparatus inside one wall. It's almost like a sculpture or a collage - sometimes it seems a shame that we won't be able to see it after the work is complete.

The south wall of the basement has been repaired prior to installation of the sheet rock. Some of the mortar between the stones had deteriorated.

On the main floor, the frames around the windows are being reconfigured. Removal of the newer wood trim reveals what appear to be original materials.