Wednesday, June 2, 2010

Week Eight







After Memorial Day weekend the crew were back at work.

The bottom section of the soffit that conceals air conditioner duct work on the main floor of the parish hall is being completed. The plan is for crown molding to be installed at its top edge after the sheetrock is sanded and painted. It will be a huge improvement from the exposed ductwork.

Ductwork is being installed in restrooms on the lower level this week. It took some ingenuity to figure out where to put it, but our hvac crew did it. We will have heat and air for the first time in renovated areas of the basement.

Electrical installation continues. It must be completed before walls can be enclosed in sheet rock.

The old mechanical chase on the north wall of the basement has been removed and will be replaced with a new one.

Week Seven Catch-up






Oops! Missed a week. It's good to be back. Here's a quick review of what happened during week seven, although now it's midway through week eight.

Installation of studs for drywall installation is just about complete. Once the electrical work is done, the sheetrock can be installed. It's here and ready to go.

Downstairs we're setting a record for neatly and efficiently concealing the most electrical and mechanical apparatus inside one wall. It's almost like a sculpture or a collage - sometimes it seems a shame that we won't be able to see it after the work is complete.

The south wall of the basement has been repaired prior to installation of the sheet rock. Some of the mortar between the stones had deteriorated.

On the main floor, the frames around the windows are being reconfigured. Removal of the newer wood trim reveals what appear to be original materials.

Sunday, May 23, 2010

Week Six Wrap-up




During week six a lot of work got done, but the visible changes were subtle. The installation of studs for drywall on the ground floor and in the basement was the big task. Sheet rock will be hung next week. First the sheet rock is secured to the studs, then it is taped and sanded multiple times to create a durable and smooth surface for painting.

Sheet rock will also be installed on the parish hall ceiling with insulation inside the ceiling joists. The insulation will help to moderate the temperature during hot and cold weather and save on heating and cooling costs.

The building work group met this week and began to select colors for various parts of the renovated area. Floor tile and counter top materials for the vestibule outside the kitchen have been chosen along with a stain color for the cabinets in that area. The group will look at samples of stained wood for the parish hall floor and wainscoting at its next meeting.

The old floor in the parish hall is gone - completely covered with plywood underlayment for the new floor. The plywood was first glued to the old flooring, then secured with wood screws. The new oak flooring will be installed on top of the plywood.

Wednesday, May 19, 2010

Week Six - Walls and Floor






Work progresses on the walls and floor of the ground floor of the parish hall. Studs for installing sheet rock are being set in place and the underlayment of the new floor is almost completely installed. Sheets of plywood are first glued to the floor, then secured with wood screws.

The walls of the vestibule outside the existing kitchen wall clearly outline the configuration of that space. Plumbing for the new upstairs rest room is beginning to take shape.

Heating and cooling the new space have been a major aspect of the work this week, but one which does not lend itself easily to visual images. The welcome news is that once the renovation is complete, the temperature in the basement will be much more comfortable both in winter and summer than it has been in the past. Ductwork is being routed that will dramatically improve the heat in the pantry storage room at the east end of the basement. This space is notorious for burst pipes during cold weather.

Monday, May 17, 2010

Week Five Wrap-up







Week five ended with the new ground floor and basement floor plans beginning to take shape. You can really start to see the new configuration of the two spaces.

The installation of plumbing in the new basement restrooms continues. It is a painstaking and detailed process of putting small segments of pipe together to fit into the allotted space and connect in all of the right spots.

On both floors, the metal framework that will support sheet rock for the new walls is being installed. On the ground floor, plywood underlayment for the new floor is being installed. As each sheet of plywood is secured, shims are placed beneath it to help level the old floor which shows the effects of 120 years of settling.

One of the most noticeable changes at the end of this week is the new room outside the kitchen on the ground floor. The existing wall between the kitchen and parish hall remains in place. The old cafeteria serving window will be filled in. Directly west of that wall is the first segment of the new stairs. They are enclosed in the new "vestibule" at the east end of the parish hall along with a prep and storage area on the north side and an ADA restroom on the south side.

Thursday, May 13, 2010

Upstairs Downstairs







Remember that stairway that went down to the basement - the one you saw as soon as you stepped inside the parish hall door? It's been transformed into a floor. An entire cart full of sheet rock is sitting on it right this minute. Floor joists were constructed in the gap in the floor where the stairway had been and they have been covered by the plywood underlayment for the new oak floor in the parish hall. We considered cleaning and refinishing the original floor. It's made of douglas fir and has lots of "character" meaning gaps, divots and uneven spots. There were serious questions about whether it could ever be cleaned well enough to refinish properly.

Initially, our building work group had hoped that the original flooring would be removed and stored for another possible use. A new oak floor will be installed in the parish hall. The problem with that idea was that the floorboards are nailed directly on top of the joists - with nothing underneath. Once the flooring was removed, the construction workers would have had to cross joists like tightrope walkers to get the new flooring installed. It simply wasn't practical, so plywood is being laid over the old flooring. It will continue on among the things seen and unseen that make up the fabric of the building. The plywood that is being laid over the old floor will give the new floor extra stability and help to level some of the uneven spots.

Getting the plywood installed is a noisy business. From the basement, the crashes and thumps sound ominous. They are frequently followed by little sluices of dust and grit that fall through the floorboards above. It's all part of getting the job done.

Meanwhile, the plumber works quietly downstairs fitting together all the small segments of pipe required for the restrooms. The guys working on the floor above did him the favor of installing the plywood directly over the area where he is working before he arrived.

Tuesday, May 11, 2010

Technical Details - Part 1






Work progresses rapidly on the renovation of the parish hall. Seeing it come together piece by piece and hearing discussions among the carpenters, electricians, plumbers and other building tradespeople gives me a sense of all of the details that have to be taken into consideration with a project like this one. Not only does everything have to fit into limited space, work properly and look good, it has to conform to the health and safety standards that are reflected in building codes.

The parish hall basement is a good example. It's a very compact space that was originally constructed in 1887. The building codes of 2010 that apply to heights of ceilings and doors, fire safety regulations, wheel chair access and modern plumbing and electricity were not in effect then, but the renovated space is required to comply with them. With this small space, the metaphor of fitting five quarts into a gallon jar applies.

To get things like ductwork and pipes where they need to be and have the finished product look good, the builders use a chase. It is an empty space enclosed by walls on either side that accommodates and hides the "inner workings" of the visible fixtures. The first and second pictures show the chase between the mens' and womens' restrooms in the basement. Toilets will eventually be attached to the pipes and bolts extending on either side of the chase shown in the third picture.

On the ground floor of the parish hall, the air conditioner ductwork which has been exposed will be enclosed in a soffit after the renovation. A soffit is the underside of any element of a building. It can be finished to resemble adjacent elements, reducing its visibility or decorated to enhance the appearance of the space. Construction of the soffit that will enclose the ductwork began today. The section above the ductwork is pictured here. Eventually portions will be attached at 90 degree angles on either side of this piece, and then another section attached on the bottom to form a box around the ductwork. The soffit is built from sheet rock which is attached to the ceiling joists above. Building code requires that enclosed spaces which are not visible to occupants of a building be shielded by non-combustible materials. This reduces the likelihood that a fire could become out of control before it is detected and action taken to evacuate the building and suppress the fire.